The situation
A remodel crew is booked for a specific night in a specific store. The crew calls off the refrigeration cases it needs, and they have to arrive after hours, exactly on time.
The date can't move. The crew is already there, waiting to receive the cases and install them.
What was at stake
When a delivery misses, the mechanical contractor still bills the retailer for the crew's time.
Across a remodel wave, that cost grows fast. A damaged case found at the store does the same damage as a late one: the crew can't install it, and the night is lost.
What Graham did
Before Graham, the construction teams leased warehouse space and ran storage and delivery themselves, and they tried shipping direct to stores with contracted carriers. On-time performance fell short of what the remodel schedule needed.
Graham replaced that with a variable cost model and four steps:
Receive early.
Cases arrive at the warehouse well ahead of the install date.
Inspect on arrival.
Every case is checked and dispositioned. Damage is found and claimed in the warehouse, not discovered at the store.
More than 15% of inbound freight from other carriers is found with claims at triage, in time to be dealt with before the install.
Hold until the crew calls it off.
Nothing ships before the store is ready for it.
Deliver on the crew's schedule.
After hours, exactly on time.
The program runs as an operating relationship, with monthly business reviews covering damage analysis and remodel and capital planning.
We represent CRST Specialized, an asset-based carrier. As an authorized CRST agent, we build programs around their fleet, network and warehouses. CRST delivers and coordinates the freight. The retailer's installer installs.
Who does what
- Graham Logistics Services
- Gets the right case to the right store, intact, on the night the crew is booked.
- CRST Specialized
- Receives, stores and delivers the cases.
- Retailer's installer
- Installs the cases.
The outcome
The variable cost model saved 60 cents of every dollar spent under the previous program. Deliveries run above 99% on time, with claims under 1%.
The program started in Dallas. A construction manager at the retailer heard how the deliveries were running and came to the warehouse to see it for himself. He made it a company-wide quality initiative, and the program went national later that year.
The lesson
Find the damage before the install crew is standing there.
At installation, it's too late. The cheapest place to catch a problem is the warehouse, days or weeks before the crew's night, when there's still time to replace a case without moving the date.