Book the Delivery to the Install Window, Not the Carrier's Schedule

Freight booked to the carrier's schedule can arrive too early to store or too late for the crew. How to set delivery appointments around the install date.

Melissa Struebing, owner and Chief Executive Officer of Graham Logistics Services

By Melissa StruebingChief Executive Officer, Graham Logistics Services

Most delivery appointments start with the carrier: when the truck can pick up, which route it's on, when it can get there. For ordinary freight, that's fine. For freight a crew is waiting on, it's backwards. The date that matters is the install, and everything else should be planned back from it.

Too early is a problem too

A late delivery is the obvious failure. An early one causes its own trouble. Freight that arrives days ahead needs somewhere safe to wait. On a construction site or in a store mid-remodel, there often isn't anywhere. Equipment sits in a hallway, gets moved twice or gets damaged before anyone installs it.

What a missed window costs

On one program Graham runs, the contractor bills for the crew's time whether the equipment shows up or not. That's the pattern on most installs: the crew, the lift and the opening date are booked around the delivery, and they're paid for either way.

  • The crew: people on the clock with nothing to install
  • Rescheduling: a second trip, a second booking, a second window
  • Recovery: expedited freight to make up the time
  • The date: an opening, go-live or start-up that moves

Plan back from the install date

  • Start with the install date and the crew's window, then set the delivery appointment inside it.
  • Confirm the site's receiving hours, and whether the delivery has to happen after hours.
  • Name a receiving contact, with a phone number, on the order before pickup.
  • Decide where freight waits if it's ready early, so it doesn't ship early.
  • Agree who tells the carrier, the site and the crew if the date moves.

The last one matters most. Install dates move. When a date changes after the freight is already moving, the delivery has to change with it, and someone has to own telling everyone.

Put a number on it

To see what a missed window costs on your program, the Late Delivery Cost Calculator uses only the numbers you enter. It shows the cost of one miss and your expected annual loss.

Run the numbers: Late Delivery Cost Calculator

More on: Retail rollouts · Technology and telecom

Frequently asked questions

What is an install window?

The time a crew, contractor or install team is booked to receive and install equipment. A delivery set to the install window arrives when the crew is ready for it, not just when the carrier can get there.

Why not just ship early to be safe?

Because early freight needs somewhere to wait. Many sites have no safe place to store equipment, so early arrivals get moved twice, left in the way or damaged before installation. Holding freight off site until its window is often safer.

Who should own a delivery date change?

One named person, decided before the freight ships. When an install date moves, the carrier, the site and the crew all need to hear it, and the delivery needs to be rebooked to the new window.